Division Street BRT Timeline

2019
DivisionConnects study begins as collaborative effort between SRTC, WSDOT, City of Spokane and Spokane County
2020
DivisionConnects analysis
2021
DivisionConnects Phase 1 Completed

STA and SRTC selected Division Street Bus Rapid Transit (BRT) Locally Preferred Alternative (LPA)
2022
STA awarded $405,000 grant for Transit Oriented Development (TOD) planning in partnership with City of Spokane and Spokane County

SRTC and partners complete DivisionConnects Phase 2

STA initiates Preliminary Engineering and Scoping phase of Division Street BRT
2023
STA Board of Directors adopts refined LPA, identifying routing to a southern terminus downtown and a northern terminus near Farwell Road and Newport Highway

FTA approves Entry into Project Development Phase which includes
  • Design and Engineering
  • Environmental Review
2024
Continue design and engineering

Begin utility coordination

Geotechnical investigations
2025
Continue design of the Minimum Operable Segment (MOS)

Submitted FTA Capital Investment Grants (CIG) Small Starts grant application

Submitted NEPA environmental review package to FTA

Continue utility coordination

Completed traffic impact analysis for the MOS
2026 (Planned)
FTA risk and readiness review:

Continue design of the MOS

Negotiate third-party agreements

Begin right-of-way acquisitions

Complete the federal and state environmental review processes

Execution of a Small Starts Single Year Grant Agreement
2027 (Planned)
Complete design of the MOS

Permitting

Complete right-of-way acquisitions

Complete third-party agreements

Initiate construction procurements

Initiate bus procurements
2028 (Planned)
Construction begins
2029 (Planned)
Construction continues

Buses arrive at STA

Operator hiring & training

Systems implementation and testing
2030 (Planned)
Construction complete

Systems implementation and testing complete

Begin revenue service on Division Street BRT
2030 +
Install BAT lanes on Division between the couplet and the “Y”

Construct Mead Transit Center

Construct pedestrian/bike facilities along Ruby St.

Construct stations north of Hawthorne Rd.

Increase service frequency

Construct active transportation improvements